Sable car GAZ-2752, 2217, 2310>> ZMZ-4063 engine>> Engine removal>> Engine removal with its partial dismantling

Engine removal with its partial dismantling

 PERFORMANCE ORDER

We disconnect from the engine all wires, drafts and hoses, we remove a radiator of system of cooling.
We remove a head of the block of cylinders (see. Removal of a head of the block of cylinders).
In need of the maximum simplification we remove a flywheel (see. Replacement of a back cuff of a cranked shaft) also we remove a starter (see. Starter removal).
We pass under the engine a cable or a strong rope and, having put on it a paw of the lift or a hook of the elevating mechanism, …

… we remove the engine from the car.

If there is no elevating device, together lift the engine by means of a steel pipe in diameter of 50-80 mm, passed under a cable. Holding the block that it did not damage wires and other details of the car, we take out it from a motor compartment.
We establish and assemble the engine in return sequence.